==Info==
==Info==


'''Member name:'''
'''Member name:''' Matt F


'''Member contact:'''
'''Member contact:''' Email, found via list.


'''Project name & pitch:''' <and any additional details>
'''Project name & pitch:''' Woodshop Rebuild. For Protospace. Encompasses: radial arm saw, pegboard & steel shelving on the Transition Projects list. Also, table saw, new workbench, table shuffling, and others. Details expanded below.


'''Storage location:'''
'''Storage location:''' Woodshop & scattered during construction


'''Project start date:'''
'''Project start date:''' 31 Aug, 2013


'''Milestone 1:''' <if any>
'''Final Deadline:''' 01 Dec, 2013


'''Deadline 1:''' <if any>
==Updates==


<Milestone 2: etc>
*''' 02 Dec, 2013 -''' Overhead shelf is half done. Waiting on workbench to size remaining build.


'''Final Deadline:'''
==Additional Details==
 
==Updates==


*''' 01 Jan 2013 -'''  <etc, for each update>
*Table saw is getting a table built for it, so it can double as a workbench.
*Travis is bringing in his personal woodworking bench with all kinds of fancy features. He's waiting on a trailer, help, and time.
*2nd metal overhead shelf is getting welded, will be where tools are stored and each will have its designated place.
*Remaining pegboard will cover back wall (I gave away most of it to members since we didn't need much).
*Radial arm saw table will be fitted somewhere.