Taz Printers: Difference between revisions

From Protospace Wiki
Jump to navigation Jump to search
No edit summary
(archived page)
 
Line 1: Line 1:
{{archived page|lastupdate=in November 2013|newpagelink=nowhere}}
==Info==
==Info==


Line 30: Line 32:
*''' 1 Oct 2013 -'''  Started building the second printer and fine tuning the first, which is out of the space.
*''' 1 Oct 2013 -'''  Started building the second printer and fine tuning the first, which is out of the space.
*''' 8 Nov 2013 -'''  Continued with second printer. Behind schedule.
*''' 8 Nov 2013 -'''  Continued with second printer. Behind schedule.
[[Category:OngoingProjects]]
[[Category:Past projects]]

Latest revision as of 06:03, 2 June 2016

This page is archived as its information is no longer current.
Last update: in November 2013.
Current information on this subject can be found at nowhere.


Info

Member name:Evan Gillespie

Member contact:5870892-8602

Project name & pitch: Craig, Alan, Joe, Dan, and I are working on 4 Taz 3d printers.

Storage location: Bay A

Project start date: September 1

Milestone 1: 1st printer done and out of the space

Deadline 1: September 30

Milestone 2: 2nd printer done and out of the space

Deadline 2: October 30


Final Deadline: Final 2 printers done and out of the space by November 30

Updates

  • 02 Sep 2013 - Stuff moved into bay
  • 09 Sep 2013 - built bed and got printer homing
  • 16 Sep 2013 - Squared Frame. Not much else.
  • 22 Sep 2013 - Started calibrating the first printer
  • 1 Oct 2013 - Started building the second printer and fine tuning the first, which is out of the space.
  • 8 Nov 2013 - Continued with second printer. Behind schedule.