Taz Printers: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
No edit summary |
||
Line 29: | Line 29: | ||
*''' 22 Sep 2013 -''' Started calibrating the first printer | *''' 22 Sep 2013 -''' Started calibrating the first printer | ||
*''' 1 Oct 2013 -''' Started building the second printer and fine tuning the first, which is out of the space. | *''' 1 Oct 2013 -''' Started building the second printer and fine tuning the first, which is out of the space. | ||
*''' 8 Nov 2013 -''' Continued with second printer. Behind schedule. | |||
[[Category:OngoingProjects]] | [[Category:OngoingProjects]] |
Revision as of 18:25, 8 November 2013
Info
Member name:Evan Gillespie
Member contact:5870892-8602
Project name & pitch: Craig, Alan, Joe, Dan, and I are working on 4 Taz 3d printers.
Storage location: Bay A
Project start date: September 1
Milestone 1: 1st printer done and out of the space
Deadline 1: September 30
Milestone 2: 2nd printer done and out of the space
Deadline 2: October 30
Final Deadline: Final 2 printers done and out of the space by November 30
Updates
- 02 Sep 2013 - Stuff moved into bay
- 09 Sep 2013 - built bed and got printer homing
- 16 Sep 2013 - Squared Frame. Not much else.
- 22 Sep 2013 - Started calibrating the first printer
- 1 Oct 2013 - Started building the second printer and fine tuning the first, which is out of the space.
- 8 Nov 2013 - Continued with second printer. Behind schedule.